FAA Academy · Lesson Companion

L17 Avtron Load Banks — Lesson Companion

Course: 40167002 Kohler Engine Generator Power Systems
Lesson: 17 — Avtron Load Banks
References: Avtron load bank schematics; ASCO 962; ASCO 434 operator manuals

How to Use This Companion

This guide is a companion to the Lesson 17 — Avtron Load Banks video. Use it to follow along during the lesson, to reinforce the major components and their functions, and to locate troubleshooting information quickly afterward.

Watch for these callouts as you read:

CalloutWhat it marks
Key PointAn important concept, operational relationship, or commonly misunderstood detail
Concept SummaryA short recap that ties a section together
Figure SummaryWhat a schematic shows and what to focus on
Troubleshooting TipPractical guidance for diagnosing a fault
CautionA safety or equipment-protection note

Lesson Overview

This lesson covers three Avtron load bank configurations used at FAA facilities:

  1. Radiator Mounted Manual Load Bank — non-shed, operates on commercial power
  2. Radiator Mounted Automatic Load Bank — load shed, operates on emergency power
  3. Remote Automatic Load Bank — outdoor automatic load shed with blower system

Each type builds on the previous. The manual load bank establishes the core circuit logic. The automatic load bank adds load shed control. The remote load bank adds airflow proving and environmental protection.

Required materials: Schematic book, ASCO 962 operator manual, ASCO 434 operator manual

Lesson objective: Given an Avtron load bank schematic, identify components, describe their functions, and describe system operation in accordance with applicable documentation.

Why Load Banks Are Used

Load banks allow testing of emergency generators under simulated load with minimal impact to facility operations.

Periodic load testing is used to verify that engine generators can sustain rated load and support facility operations during an emergency power event.

ConditionStandard Practice
Scheduled maintenanceLoad test performed for mobile and standby emergency generators
After non-routine maintenanceLoad test performed on NAS power systems

What resistive load banks do:

  • Convert electrical energy to heat through resistive elements
  • Apply a controlled load directly to the generator output
  • Allow the generator to be tested at operating load without loading the facility
  • Verify that the standby power system is ready to support facility operations

Typical load shed operating target: 50–80% of rated generator capacity

Operating below 50% risks wet-stacking in diesel engines. Operating above 80% risks overload. All three load bank types are designed to keep the generator within this range during testing.

Note: Specific FAA load-testing requirements and acceptable test loading methods are defined by current maintenance guidance and may vary by equipment type and testing objective.

Load Bank Types Comparison

FeatureManualAutomaticRemote Automatic
LocationOn generator radiatorOn generator radiatorOutdoors, remote from engine
ATS sourceCommercial / normalEmergencyEmergency
ATS feature14A14B14B
ATS contactsTS12, TS13TS10, TS11TS10, TS11
Load controlTechnician (manual)Automatic (load shed assembly)Automatic (load shed assembly)
K99 requiredYesYesYes
CT1NoYesYes
Load shed assemblyNoYesYes
K100 / K101NoYes (FAA mod)Yes (FAA mod)
BlowerNo (uses radiator airflow)No (uses radiator airflow)Yes (208V AC)
S61 airflow switchNoNoYes (900 CFM)
S62 / HR1NoNoYes (cold weather)
S60Yes (350°F/310°F)Yes (350°F/310°F)Yes (350°F/310°F)
DS21 meaningOver tempOver tempAir fail

Radiator Mounted Manual Load Bank

Manual Load Bank
Figure 1 — Radiator Mounted Manual Load Bank schematic (Drawing D26193, 30KW, 208V, 3PH)

What It Is

The manual load bank is a non-shed load bank. "Non-shed" means:

  • It has no automatic load shedding capability
  • All load steps are applied manually by the technician
  • It is disabled by design during emergency power operation

It operates only while the ATS is on commercial power. When the ATS transfers to emergency, control power is removed and the load bank shuts down automatically.

Control Panel Components

DesignationFunction
TB1Main terminal board — all control panel I/O
F110A protective fuse — panel overcurrent protection
S23Emergency stop switch (normally closed) — removes all 120V AC from panel when opened
S20Control power switch (on/off)
DS20Control power LED — lit when 120V AC is active in panel
K99Gatekeeper relay — must energize before any load can be applied
K99-4 / K99-7Normally open contacts of K99 — close when K99 energizes
S21Master load switch — enables individual load step switches
S1 / S2 / S3Individual load step switches (10 kW each, 30 kW total)
DS21Over temperature LED — illuminates when S60 trips

Load Bank Components

DesignationFunction
TB11Main terminal board — load bank I/O
RA1Resistive heating elements — the actual load (3-phase, 208V)
K1 / K2 / K3Load step coils — normally open contacts close to apply RA1 circuits
CT2 / CT3Current transformers (optional) — for panel meter only
F5 / F6 / F7Meter protection fuses (optional)
S60Over temperature switch — removes K99 control power at 350°F

How Control Power Flows — Manual Load Bank

Control power must pass through every item in this path before K99 can energize:

120V AC source
    → TB1-1
    → F1 (10A fuse)
    → S23 (emergency stop, normally closed)
    → TB1-8 (exits control panel)
    → TS12 / TS13 (ATS feature 14A — must be on commercial)
    → TB1-7 (returns to control panel)
    → S20 (control power switch, closed)
    → TB1-6 (exits to load bank)
    → TB11-6 (enters load bank)
    → S60 contact 1-to-3 (normal, not over temp)
    → TB11-4 (exits load bank)
    → TB1-4 (returns to control panel)
    → K99 coil → K99 ENERGIZES

When K99 energizes: K99-4 and K99-7 close → DS20 illuminates → load bank ready.

Applying Load — Procedure

  1. Close S20 (control power switch) → DS20 illuminates, K99 energizes
  2. Close S21 (master load switch)
  3. Apply load steps one at a time
  4. Target: 50–80% of rated generator load
  5. For the 30 kW schematic: apply any two steps (20 kW) to reach target range

Valid two-step combinations: S1+S2 | S1+S3 | S2+S3

Shutdown Conditions

The manual load bank stops operating when any of the following occur:

ConditionWhat happens electrically
Load step switches opened (S1/S2/S3)Load removed from that step
Master load switch opened (S21)All load steps removed
Emergency stop opened (S23)All 120V AC removed from panel
Control power switch opened (S20)K99 de-energizes
Loss of commercial powerTS12/TS13 open
ATS transfers to emergencyTS12/TS13 open
Over temperature conditionS60 trips, K99 de-energizes

Over Temperature Protection — S60

S60 is the most important safety device in the load bank.

StateTemperatureContact positionEffect
NormalBelow 350°FContact 1 → Contact 3K99 control path complete
Trip350°F or aboveContact 1 → Contact 2K99 coil loses power; DS21 illuminates; load bank de-energizes
Reset310°F or belowReturns to 1 → 3Load bank operation may resume

When S60 trips:

  • K99 de-energizes
  • DS21 (over temp LED) illuminates in the control panel
  • Load bank is de-energized and loses all load
  • Engine continues running
  • Technician loses load bank control until S60 resets

Troubleshooting — Manual Load Bank

SymptomCheck
DS20 off after closing S20F1 blown? S23 open? ATS on commercial? TS12/TS13 closed?
DS20 on, no load appliesS21 closed? K99-4/K99-7 contacts closing? S60 not tripped (check DS21)?
Load bank shuts down during testDS21 lit (over temp)? ATS transferred to emergency? S20/S23 position?
DS21 illuminatedS60 has tripped at 350°F. Do not operate. Allow cool-down below 310°F
Specific load step does not applyK1/K2/K3 coil continuity. TB11 wiring at that step terminal

Radiator Mounted Automatic Load Bank

Automatic Load Bank
Figure 2 — Radiator Mounted Automatic Load Bank schematic (Drawing D27496)

What It Is

The automatic load bank is a load shed system. It:

  • Operates only while the ATS is on emergency power
  • Automatically adds load bank steps when facility load decreases
  • Automatically removes load bank steps when facility load increases
  • Maintains the generator in the 50–80% load range without technician intervention

FAA application: Used on Kohler generator sets that do not have an Electronic Control Module (ECM), including many first-generation Kohlers.

Feature 14B and ATS Contacts

ItemDetail
Feature 14BASCO ATS auxiliary contact feature for emergency source
TS10 / TS11Close when ATS is on emergency — enable automatic load shed
Schematic Note 3All ATS contacts shown in normal (commercial) position. TS10/TS11 are shown open — they close on emergency transfer
FAA triangle symbolMarks K100 and K101 as FAA-required modifications

Control Panel Changes

The automatic load bank shares most control panel components with the manual version. Key changes:

ComponentChange
S20Three-position switch: Auto / Off / Manual (was on/off)
DS30New LED — Auto On indicator
K100New FAA modification relay
K101New FAA modification relay

K100 and K101 — The FAA Modification

When the ATS transfers to emergency, TS10/TS11 close and energize both K100 and K101.

K100:

  • Opens normally closed contacts in series with S1, S2, and S3
  • Prevents the technician from manually adding load steps while the generator is carrying actual emergency facility load
  • Protects against manual engine overload

K101:

  • Opens normally closed contacts in series with S4 — disables manual step S4
  • Closes normally open contacts — routes 120V AC control power through TB1-9 and conduit to TB11-9, enabling the load shed assembly at connector J1
K100/K101 stateATS positionManual stepsLoad shed assembly
De-energizedCommercialAvailableNot powered
EnergizedEmergencyDisabledPowered through K101

CT1 and Load Monitoring

CT1 is the current transformer that provides feedback to the automatic load shed assembly.

  • CT1 monitors the generator output current, which reflects the facility load being carried by the generator
  • CT1 converts the high current levels to a proportional lower-level signal
  • This signal feeds the load shed assembly at connector J1, terminals 1 and 2
  • The load shed assembly uses the CT1 signal to determine when to add or remove load steps

Automatic Operation Sequence

  1. 120V AC enters panel at TB1-1 → F1 → S23 → S20 (Auto position) → DS20 → TB1-6 → TB11-6 → S60 → TB11-4 → TB1-4 → K99 energizes
  2. ATS transfers to emergency → TS10/TS11 close → K100 and K101 energize
  3. K100 opens S1/S2/S3 manual paths — manual step control disabled
  4. K101 N/O contacts close → 120V AC to TB1-9 → TB11-9 → load shed assembly connector J1
  5. K99-4 and K99-7 close → control voltage to auto on LED and to load shed assembly
  6. Load shed assembly begins automatic step control based on CT1 feedback

Detail A-A Explained

Detail A-A
Figure 3 — Detail A-A: Load Shed Assembly circuit, used in both the Radiator Mounted Automatic and Remote Automatic Load Bank schematics

What It Is

Detail A-A is the load shed assembly control circuit. It is shown as an inset on both the radiator-mounted automatic and remote automatic load bank schematics.

Purpose: Keep the generator loaded at 50–80% of rated output by continuously monitoring the facility load carried by the generator and automatically adding or removing load bank steps.

Inputs — Connector J1

TerminalSignalSource
J1-1CT input (+)CT1 — facility load current signal
J1-2CT input (–)CT1 — return
J1-11120V AC control voltageFrom K101 N/O contacts via TB11-9
J1-12Control voltage return / commonReturn path

Outputs — Connector J2

The load shed assembly sends load step commands out through J2:

TerminalStepDestination
J2-2Step 1Commands K1 in load bank → applies RA1 circuit 1
J2-4Step 2Commands K2 in load bank → applies RA1 circuit 2
J2-6Step 3Commands K3 in load bank → applies RA1 circuit 3

Load Step Control Relays — K41, K42, K43

K41, K42, and K43 are the load shed controller's output relays. Each corresponds to one load step.

Important: these relays use inverse logic.

K4x stateLoad step
EnergizedLoad step is removed
De-energizedLoad step is applied

K41, K42, K43 relay terminals visible on Detail A-A:

TerminalFunction
A1 / A2Coil terminals — load shed controller drives these
E3Normally closed contact — carries load step path when relay is de-energized
MNormally open contact

Timing Relays — K40, K31, K32, K33

K40, K31, K32, and K33 are the sequencing relays that gate each load step in a timed chain. They prevent all load steps from being applied simultaneously.

RelayTime delayEnergized byEnables
K405 secondsJ1-11 (120V AC)K31 coil path (contact 15)
K313 secondsK40 contact 15K32 coil path (contact 15) + Step 1 output (contact 25/28 → J2-2)
K323 secondsK31 contact 15K33 coil path (contact 15) + Step 2 output (contact 25/28 → J2-4)
K333 secondsK32 contact 15Step 3 output only (contact 25/28 → J2-6)

Total minimum time from power application to all steps available:
5 + 3 + 3 + 3 = 14 seconds

How Each K3x Relay Works

Each K3x relay has three contact functions:

ContactNumberFunction
Chain-forward15Provides coil path to the next relay in sequence
K4x gate18Gates the corresponding K4x relay coil circuit
Step output25 → 28 → J2Provides the actual load step command to J2

For a load step to apply, two conditions must both be true:

  1. The K3x sequencing relay must be energized (contact 18 closed — gating K4x)
  2. The K4x relay must be de-energized (E3 contacts in closed position)

Neither condition alone is sufficient.

Load Shed Operating Logic

Example: 100 kW generator. Target = 50–80 kW.

Facility load is in range (50–80 kW):

  • CT1 confirms optimal loading
  • Load shed controller energizes K41, K42, K43
  • K41/K42/K43 E3 contacts open → all load bank steps removed
  • Load bank on standby

Facility load falls below 50 kW:

  • CT1 signals low load
  • K41 de-energizes → K41 E3 contacts close → K31 path gates → J2-2 signals K1 → Step 1 applied
  • Still below 50 kW: K42 de-energizes → K32 → J2-4 → K2 → Step 2 applied
  • Still below 50 kW: K43 de-energizes → K33 → J2-6 → K3 → Step 3 applied
  • Continues until CT1 confirms 50–80% range

Facility load rises above 80 kW:

  • K43 energizes → K33 de-energizes → Step 3 removed
  • Still above 80 kW: K42 energizes → K32 de-energizes → Step 2 removed
  • Still above 80 kW: K41 energizes → K31 de-energizes → Step 1 removed
  • Continues until generator returns to range or all steps removed

Load steps are applied in order: 1 → 2 → 3
Load steps are removed in order: 3 → 2 → 1

Remote Automatic Load Bank

Remote Automatic Load Bank
Figure 4 — Remote Automatic Load Bank schematic (Drawing D07714, Sheet 16)

What Is the Same

The remote automatic load bank uses the same core logic as the radiator-mounted automatic load bank:

  • 120V AC control power
  • K99 gatekeeper relay (required)
  • Feature 14B / TS10/TS11 for automatic enable
  • K100 and K101 FAA modification relays
  • Load shed assembly — Detail A-A circuit
  • CT1 for load monitoring
  • K40/K31/K32/K33 timing sequence
  • K41/K42/K43 load step control
  • S60 over temperature protection

What Is Different

The remote load bank is located outside, away from the engine-generator set. Without access to radiator airflow, the unit requires a blower motor to move air through the resistive elements.

Before any load can be applied, the blower must prove it has reached 900 CFM. K99 will not energize until airflow is proven.

New components unique to the remote load bank:

DesignationFunction
S61Airflow switch — proves 900 CFM before enabling K99
K22Blower control relay — N/O contacts supply power to blower when energized
K21Blower thermal overload relay — bimetal strip trips on prolonged overcurrent
DS21"Air Fail" LED — lit when airflow is below 900 CFM or K99 is de-energized (note: different meaning than manual/auto load bank DS21)
DS22"Blower Power" LED — lit when blower is powered
S62Low temperature switch — closes below 50°F
HR1Internal heater — cold weather protection
TB12Blower power terminal board (208V AC at terminals 1, 2, 3)
F2 / F3 / F4Blower circuit fuses
Pitot tubeAirflow velocity sensor — provides signal to S61

Blower Circuit

The blower operates on 208V AC supplied through TB12.

ComponentRole
K22 coilEnergized by 120V AC control power when system is powered on
K22 N/O contactsClose to supply 208V AC from TB12 through F2/F3/F4 to blower motor
K21 N/C contactsIn series with blower motor — normally closed; trips open on prolonged overcurrent
F2 / F3 / F4Fuse protection for blower motor circuit

Normal Startup — Airflow Proving Sequence

At initial power-up, two things happen simultaneously:

Path 1 — Air fail indication:
S60 (normal, 1→3) → S61 (normal, below 900 CFM) → exits at TB11-5 → TB1-5 → DS21 Air Fail illuminates

Path 2 — Blower start:
K21 N/C contacts → K22 coil energizes → K22 contacts close → 208V AC through F2/F3/F4 → through K21 motor contacts → blower startsDS22 Blower Power illuminates

At startup, both DS21 and DS22 are lit simultaneously. This is normal.

TimeDS21 (Air Fail)DS22 (Blower Power)K99System state
Power appliedONONDe-energizedNormal — blower spinning up
Blower at 900 CFMOFFONEnergizedReady — load shed active
K21 tripONOFFDe-energizedFault — investigate

Cold Weather Devices

ConditionDeviceAction
Ambient drops below 50°FS62 closesHR1 heater energizes
HR1 energizedHR1 heaterPrevents freezing inside the load bank enclosure

K21 Overload — Cascade Shutdown

If the blower motor draws excessive current for a prolonged period:

K21 bimetal strip heats → K21 contacts open
    → K22 coil de-energizes → K22 contacts open
    → 208V AC removed from blower motor
    → Blower decelerates below 900 CFM
    → S61 switches back to normal position
    → K99 coil loses power → K99 de-energizes
    → Load shed assembly de-powered
    → Load bank inoperable (auto and manual)

Result: DS21 (Air Fail) ON | DS22 (Blower Power) OFF

Engine continues running. Only the load bank is disabled.

Outdoor Maintenance Awareness

Remote load banks are typically located outdoors. Before opening the enclosure:

  • Visually inspect the exterior for signs of nesting (mud tubes, insect activity, droppings)
  • Use a flashlight to inspect the interior before inserting hands
  • Documented enclosure residents: snakes, mice, rabbits, squirrels, bees, wasps, spiders

Pitot tube blockage:
The pitot tube provides the airflow velocity signal to S61. Mud daubers (a species of wasp) are documented to nest inside the pitot tube. A blocked pitot tube prevents S61 from sensing adequate airflow — even when the blower is running at full speed.

Result of blocked pitot tube: DS21 (Air Fail) remains lit, K99 does not energize, load bank inoperable.

Concept Review

Load Bank Types and ATS Conditions

  • Manual = commercial power (feature 14A, TS12/TS13)
  • Automatic = emergency power (feature 14B, TS10/TS11)
  • Remote = emergency power + airflow proven (feature 14B + S61)

K99 — The Gatekeeper

  • Required for all three load bank types
  • Required in both manual and automatic modes
  • Cannot be bypassed
  • Failure = load bank inoperable

S60 Temperatures

  • Trip: 350°F
  • Reset: 310°F
  • Contact change: 1→3 (normal) to 1→2 (over temp)

Timing Relay Sequence

  • K40: 5 seconds
  • K31: 3 seconds
  • K32: 3 seconds
  • K33: 3 seconds
  • Total minimum: 14 seconds

K41/K42/K43 Logic

  • Energized = load step removed
  • De-energized = load step applied

Seven Manual Shutdown Conditions

  1. Load step switches opened
  2. Master load switch (S21) opened
  3. Emergency stop (S23) opened
  4. Control power switch (S20) opened
  5. Loss of commercial power
  6. ATS transfers to emergency
  7. Over temperature (S60 trips)

S61 Threshold

  • 900 CFM — remote load bank only
  • Below 900 CFM: S61 routes to DS21 air fail
  • At 900 CFM: S61 switches to K99 coil path

S62 Threshold

  • Closes below 50°F — remote load bank only
  • Energizes HR1 heater

K100 / K101 Functions

  • K100: Energized by TS10/TS11; disables manual steps S1, S2, S3
  • K101: Energized by TS10/TS11; disables manual step S4; closes N/O contacts to power load shed assembly

Optimal Generator Load Range

  • 50–80% of rated capacity
  • Example: 100 kW engine → target 50–80 kW

CT1 Purpose

  • Monitors facility load being carried by the generator
  • Provides feedback signal to load shed assembly at J1-1 and J1-2
  • Enables automatic load step add/remove decisions

Key Terms

TermDefinition
Load bankEquipment that applies a controlled resistive load to a generator for testing
Non-shedManual load bank with no automatic load shedding capability
Load shedAutomatic function that removes load bank steps when facility demand increases
Resistive loadLoad that converts electrical energy directly to heat; purely resistive (unity power factor)
Feature 14AASCO ATS auxiliary contact feature; contacts close on commercial source
Feature 14BASCO ATS auxiliary contact feature; contacts close on emergency source
K99Master enable / gatekeeper relay; required for all load bank operation
CT1Current transformer; monitors facility load carried by generator; feeds load shed assembly
Load shed assemblyControl circuit (Detail A-A) that automatically manages load steps based on CT1 feedback
Gatekeeper relayK99; must be energized before any load can be applied
S60Over temperature switch in the load bank; trips at 350°F, resets at 310°F
S61Airflow switch in remote load bank; requires 900 CFM before K99 can energize
K21Blower thermal overload relay (bimetal strip); trips on prolonged overcurrent
K22Blower control relay; N/O contacts supply power to blower
Pitot tubeAirflow velocity sensor providing signal to S61
K40/K31/K32/K33Timing relay chain in the load shed assembly; gates load step sequencing
K41/K42/K43Load shed controller output relays; de-energized = step applied; energized = step removed
FAA modificationCircuit change identified by triangle symbol on schematic; K100 and K101 are FAA modifications
TB1 / TB11Control panel / load bank terminal boards with 1:1 terminal correspondence
Wet-stackingDiesel engine condition caused by prolonged light loading; load testing prevents this

Lesson Summary

Three load bank types — different sources, same goal:

TypeWhen it operatesHow load is controlled
ManualATS on commercialTechnician applies steps manually
AutomaticATS on emergencyLoad shed assembly responds to CT1
Remote AutomaticATS on emergency + 900 CFM airflow provenLoad shed assembly responds to CT1

K99 is the common thread. Every load bank type, every operating mode, requires K99. If K99 cannot energize, the load bank cannot operate. Understanding what K99 needs — and what can prevent it from energizing — is the foundation of load bank troubleshooting.

The automatic load shed assembly (Detail A-A) adds two relay groups:

  • K40/K31/K32/K33 — a 14-second timed sequencing chain that gates step availability
  • K41/K42/K43 — the controller's output relays that apply or remove steps based on CT1 feedback

Both relay groups must cooperate for a load step to apply or be removed.

The remote load bank adds one requirement: the blower must prove 900 CFM airflow before K99 can energize. Every additional component in the remote load bank (S61, K21, K22, DS21, DS22, pitot tube) serves this one function.

Periodic load testing and post-maintenance testing of applicable engine generators are standard practice in aviation facility maintenance. Proper maintenance and troubleshooting skills directly support mission-critical facility uptime.

L17 Avtron Load Banks — Lesson Companion
Course: 40167002 Kohler Engine Generator Power Systems
References: Avtron load bank schematics D26193, D27496, D07714; ASCO 962; ASCO 434